What information belongs in a genset RFQ?

Use this checklist to give each supplier the same electrical, mechanical, controls, testing, and commercial scope.

THE SHORT VERSION

Send the one line, load information, site conditions, scope boundaries, testing requirement, and delivery date together. Missing scope creates allowances, exclusions, and incomparable bids.

01

Electrical and load information

Provide both steady-state demand and transient requirements. If detailed studies are not complete, label every assumption and identify the largest motors and nonlinear loads.

  • Required kW and kVA
  • Voltage, phase, frequency, and wire configuration
  • Load list and load steps
  • Motor starting and UPS or VFD loads
  • Grounding and neutral arrangement
  • Breaker and fault-current requirements
02

Mechanical and site information

Describe the installation instead of relying on a generic outdoor-enclosure selection.

  • Diesel, natural gas, propane, or dual fuel
  • Indoor, outdoor, rooftop, or containerized
  • Ambient temperature and altitude
  • Sound target and measurement distance
  • Wind, seismic, corrosion, and snow requirements
  • Ventilation, radiator, and exhaust constraints
03

Controls and system integration

Include the ATS or paralleling sequence and every external interface. Clarify who supplies and programs each piece.

  • Remote start and stop
  • ATS quantity and sequence
  • Paralleling and load sharing
  • Load shed and priority blocks
  • BMS or SCADA protocol
  • Remote annunciation and monitoring
04

Commercial scope

State the requested date, destination, and services. A low equipment price can conceal freight, startup, testing, accessories, and scope gaps.

  • Required on-site date
  • Freight and unloading responsibility
  • Startup and commissioning
  • Factory and field testing
  • Training and documentation
  • Warranty start and duration

QUOTE CHECKLIST

Information to send with the RFQ

  • 01One line
  • 02Equipment specification
  • 03Load list
  • 04Site plan or layout
  • 05Required date
  • 06Scope of supply
  • 07Testing requirements
  • 08Known alternates
Build your RFQ ↗

Sources and further reading

Project requirements and adopted codes control. Use these manufacturer and standards-organization resources as technical starting points.